地鐵4號線李嶗區間暗挖始發洞管棚施工完成

青(qing)島地鐵4號(hao)線(xian)李家下莊站大里程端暗挖始發洞(dong)20m管棚(peng)施工于5月20日(ri)正式開(kai)工,于6月22日(ri)完(wan)成左右(you)兩洞(dong)管棚(peng)施工。


據悉,李嶗區間設置(zhi)φ76壁厚8mm管(guan)(guan)棚超前(qian)預加(jia)固(gu),長(chang)度為(wei)20m。鋼管(guan)(guan)采(cai)用直徑76mm璧厚8mm的熱軋無縫鋼管(guan)(guan),環(huan)向間距0.4m,外插角5-10°,管(guan)(guan)棚采(cai)用分節安裝,相(xiang)鄰兩鋼管(guan)(guan)的接頭要(yao)錯(cuo)(cuo)接,錯(cuo)(cuo)接長(chang)度不(bu)小于1m,鋼管(guan)(guan)上注漿孔(kong),孔(kong)徑10mm,孔(kong)間距150mm,梅(mei)花(hua)形布(bu)置(zhi),鋼管(guan)(guan)尾(wei)部(bu)2米作為(wei)止漿段,不(bu)設置(zhi)注漿孔(kong),注漿結束后,用m10水泥砂(sha)漿充滿(man)鋼管(guan)(guan)。


為(wei)保(bao)證(zheng)施工(gong)進(jin)度,項目(mu)部制定了(le)合理有(you)效的施工(gong)節點工(gong)期目(mu)標(biao),工(gong)程技術(shu)部提前(qian)對施工(gong)班組以及(ji)相(xiang)關人員(yuan)進(jin)行技術(shu)交底,使施工(gong)人員(yuan)對管(guan)棚施工(gong)的工(gong)序工(gong)法做到應知應會;以確保(bao)管(guan)棚施工(gong)的質(zhi)量達標(biao)。


管(guan)棚施工(gong)(gong)的完成(cheng)為下(xia)步TBM掘進、暗挖施工(gong)(gong)創(chuang)造安全、穩定的施工(gong)(gong)條(tiao)件。


圖片1.jpg

李嶗區間管棚施(shi)工